Eskom pushes power cuts to stage 6 ‘until further notice’
Updated | By Nushera Soodyal
Eskom says stage 6
load shedding will be continuously implemented from 4pm on Wednesday until
further notice
Initially, the power utility said that stage 6 would only be implemented between 4pm and 5am.
Eskom spokesperson, Sikonathi Mantshansha says they have had to increase the power cuts due to severe capacity constraints.
"Eskom will continue to manage the limited emergency generation reserves to supplement generation capacity. Eskom will publish a further update as soon as there are any significant changes."
“Eleven generators amounting to 5 084MW of capacity suffered breakdowns since Tuesday morning, further reducing available capacity and necessitating the increase in the stages of loadshedding.
READ: No concrete actions to end load shedding, says expert
“These were a unit each at the Camden, Duvha, Grootvlei, Hendrina, Kendal, and two units each at Kriel, Majuba and Matla power stations.”
A unit each at Camden, Duvha, Hendrina, Kriel, Matimba and Matla power stations has returned to service, representing 2 540MW of capacity.
MORE ON ECR
Show's Stories
-
Woman swipes card at wishing well
Could this be the most ridiculous thing or the smartest that ever happen...
Danny Guselli 20 hours ago -
Man falls off motorbike while holding baby
This is why you should not chill on something that can be flimsy, especi...
Danny Guselli 20 hours ago