Stage 2 load shedding to continue on Sunday

Stage 2 load shedding to continue on Sunday

Eskom will continue to implement stage 2 load shedding on Sunday.

Duvha Power Station Eskom  - AFP
MARCO LONGARI / AFP

The struggling power utility implemented the rolling blackouts on Saturday afternoon after a unit each at Camden and Medupi power stations and two at Grootvlei broke down.

 

Eskom spokesperson Sikonathi Mantshantsha says it will be rolling blackouts until further notice.

 READ: Black Sash: Sassa system denying people rightful grants

"A delay in returning a generating unit to service at Lethabo Power Station has contributed to the capacity shortages. The load shedding will continue until further notice. 

 

"We currently have 5 244MW on planned maintenance, while another 16 455MW of capacity is unavailable due to breakdowns."