Stage 4 load shedding will kick on Tuesday afternoon and Eskom says it will stay in this stage for the next 24 hours.

CANDLE
Unsplash

The power utility says stage 5 load shedding will then be implemented from 4pm tomorrow until 5am on Thursday.


Eskom's Menzi Mngomezulu says this pattern will continue until further notice.


READ: DA wants ad hoc committee to probe Eskom corruption


"Breakdowns at a unit each at Duvha, Lethabo, Majuba and Tutuka power stations caused units to be taken offline for repairs. 


"The delay in returning a unit each to service at Arnot, Camden, Duvha and Kendal power stations are contributing to the current capacity constraints. 


"Breakdowns currently amount to 19 031MW of generating capacity while 4 174MW of generating capacity is out of service for planned maintenance."